Sarulla Geothermal Power Plant, Indonesia

Project Profile
  • Name : Sarulla Geothermal Power Plant
  • Location : Sumatera, Indonesia
  • Method : Deep Cement Mixing
Construction duration
  • From : 2015.05
  • To : 2015.09

Sarulla Geothermal Power Plant is located beside Toba Lake which was a volcanic in history. The project site contains a lot of Tuff soil which is expansive when meeting water. Deep Cement Mixing method is used to improve the loose Tuff soil for stabilizing the whole backfill area.