Jawa 7 Power Plant, Indonesia

Project Profile
  • Name :Jawa 7 Power Plant
  • Location : Jawa, Indonesia
  • Method : VCM
Construction duration
  • From : 2016.05
  • To : 2017.07

Jawa 7 Power Plant is one of the largest coal fired power plant with 2*1000 MW capacity in Indonesia. The project is located at low land area with a lot of fish pool and swampy area. Vacuum Consolidation method is used to improve the soft clay to help the overall construction period to fulfill the very tight period requirement.